It’s not often we encounter a project like this! We have successfully completed the installation of a piled slab at a specialised site. The project specifics include:
- Installation of eight no. 150mm piles, each reaching a depth of 4 meters.
- Implementation of heave protection as advised by the structural engineer.
- Placement of two layers of A393 mesh with lacer bars.
Following a thorough inspection by Building Control, C35 concrete was poured to finalise the structure.